Saint-Gobain (Isover) Runcorn

 
Balmoral Tanks case study

Saint-Gobain produces insulation materials for the housing market. Due to the nature of the product it is imperative that the manufacturing plant functions 24/7, 365 days a year, with a three week period set aside for essential regular maintenance.

It was critical that the replacement tank, together with steel framework, be installed within this window of opportunity, and the need for tank installers to work alongside the on-site engineers who first had to remove the old tank, which was to be reused, prior to dismantling the outdated tank which was being replaced.

Saint-Gobain had full confidence in Balmoral’s ability to complete the project within the tight timeframe as the company had previously supplied and assembled a tank and frame on the site several years earlier which is still functioning perfectly.

Application Cooling tower water tank
Tank type Hot press steel sectional tank
Dimensions

12.2 x 4.88 x 2.44m

Capacity 145.27m3
Scope of work Design, manufacture and installation
Contact us to find out how we can help you solve your current technical challenge

CASE STUDIES

Global project track record


Case studies

DOWNLOADS

Literature and certification


Downloads

OUR COMPANY

Trusted. Innovative. Collaborative.


Our promise

Balmoral Tanks Ltd
Contact us | Locations
Reg No. SC300656

Search